This page covers residential fence work inside the municipal boundaries of the City of Jasper in Dubois County, Indiana. Jasper administers its own fence permits and Unified Development Ordinance.

Jasper requires a fence permit and a scaled site plan. Most fences must stand at least two feet inside the property line, with an exception for the A1 and A2 agricultural districts. Residential height limits are four feet in front, six feet at the side and eight feet at the rear; both street fronts of a corner lot have the front-yard limit. Wood and vinyl appear on the application, while chain-link and flexible wire fencing have frontage restrictions. Mixed-Use Overlay rules, residential design standards, sight triangles, easements, drainage and pool barriers can change the project requirements. Updated October 2026.

Quick questionJasper answer
Permit or approvalA City fence permit is required before erecting a fence or wall. Submit the application and scaled site plan; the fence permit fee is $35. Site-specific approvals can also apply.
Typical fence heightResidential maximums are 4 feet front, 6 feet side and 8 feet rear. Both street-front yards on a corner lot count as front yards. Through lots have a separate front/rear assignment.
Placement & property linesAt least 2 feet from property lines except in A1/A2 agricultural districts. Public rights-of-way, easements, required sight areas and applicable design standards impose additional limits.
Common fence materialsWood: recognized on the application. Vinyl/PVC: the application lists vinyl but does not separately name PVC. Chain-link: recognized on the application but restricted in residential front yards and certain design/overlay settings.
Important local conditionsFence rules may be further affected by corner and through lots, residential design standards, the Mixed-Use Overlay, pool use, floodplain/floodway conditions, regulated drains, utility access and recorded easements or development conditions.
Official local resourceCity of Jasper Fence Permit Application and Site Plan Guide

The table is a quick reference. The corresponding sections below explain the additional requirements and exceptions. Before purchasing materials or beginning construction, read the sections that apply to the property, review the linked official sources and confirm site-specific questions with the Community Development & Planning Department or the office responsible for the particular issue.

GOVERNANCE

The City of Jasper Common Council adopts the City’s ordinances. The Community Development & Planning Department administers fence permits and the Jasper Unified Development Ordinance, including the fence and wall standards in Section 7.14. The Jasper Advisory Plan Commission handles applicable planning and subdivision matters, and the Jasper Board of Zoning Appeals handles variances and appeals within its authority.

The Plan Commission’s jurisdiction includes the City and a specifically described extra-territorial area extending up to two miles beyond the municipal boundary, identified in a description or map filed with the Dubois County Recorder. This page’s publication scope is the City itself. The Community Development & Planning Department issues both fence permits and improvement location permits, the latter also described locally as building permits.

Several offices have distinct responsibilities. The Director of Community Development and Planning serves as local Floodplain Administrator. The City Engineer and Storm Water Coordinator administer relevant stormwater and drainage reviews; the Street Department handles applicable street and drainage inspections. The Board of Public Works and Safety has responsibilities under the City’s public-work and drainage rules. The Dubois County Surveyor and County Drainage Board have statutory roles where a regulated drain is involved, subject to any lawful transfer of jurisdiction.

The Jasper Code of Ordinances separately addresses pools, animal enclosures, utility access, public-street excavation, stormwater and floodplain development. Indiana’s statewide construction rules also apply within their scope. The 2020 Indiana Residential Code, which adopts the 2018 International Residential Code with Indiana amendments, governs the covered residential construction; local permits and inspections remain separate administrative requirements.

PERMIT AND APPROVAL REQUIREMENTS

• Fence permit before construction: UDO Section 10.1(C)(6) requires a permit before a fence or wall is erected. The City’s permit brochure requires the fence form for all types of fences. The fee is $35, payable at approval. The Community Development & Planning Department requires seven business days after all required forms and drawings are submitted for application review. Work may begin only after approval; the Department issues the appropriate job-site placards.

• Application and site plan: The application requests the owner and contact information, location and legal description, contractor information, fence type, fence height and overall height from grade, and whether the lot is an interior or corner lot or lies at a street/alley corner. The owner certifies the information. Submit a scaled overhead site plan showing a north arrow, lot size and dimensions, street names, existing and proposed structures, rights-of-way, the fence line, and setback distances from every property boundary. Include easement and driveway locations and dimensions and measurements on all four sides. The brochure also calls for staking or flagging the proposed work before submission. Staff may check the site before approval and after construction.

• Survey staking near a setback line: Under UDO Section 4.17(C)(2)(e), when an ordinance or variance permits a building, fence or wall less than five feet from a setback line, the affected boundary-line corners must be staked before permit approval by an Indiana-licensed professional land surveyor. The requirement refers to the setback line, while the ordinary two-foot fence setback is measured from the property line.

• Building-code and zoning documents: Indiana replaced model IRC Section R105 with its own additions-and-alterations text; the model seven-foot fence permit exemption is not part of Indiana’s residential permit framework. Jasper’s express fence permit applies. The City also administers improvement location permits and a separate Zoning Compliance Letter. A Zoning Compliance Letter requires owner information and a scaled site plan, describes zoning compliance on its date, and is not itself a permit or a guarantee of future permit approval.

• Pool with fence applications: Jasper publishes a combined Pool with Fence Permit Application. It requests the pool type and minimum/maximum depth, fence height, contractors, and a site plan locating the pool and fence with boundary setbacks. The owner acknowledges that a fence must be erected before using the pool. Published pool fees are $50 for an above-ground pool and $75 for an in-ground pool, with a pool/fence permit requirement. The permit brochure uses water depth over 36 inches for its pool-permit trigger; the local private-pool enclosure definition uses a separate depth threshold described below. The City’s fee documents list the fence fee separately.

• Residential design, overlays and planned developments: The residential design standards and Mixed-Use Overlay can add fence conditions. In the Mixed-Use Overlay, individual single-family uses may receive administrative review; Commission development-plan approval applies when they are part of a major subdivision. The overlay’s general development-plan trigger for new development or expansion exceeding 30 percent of existing gross floor area is a separate development condition. In the US 231 Thoroughfare Overlay, the overlay standards apply to new development and existing structures expanded by 50 percent or more, but individual single- or two-family lots are excluded except as part of a major subdivision. Mixed-Use Overlay provisions take precedence over Thoroughfare Overlay provisions where they overlap, with underlying standards filling unstated matters. Applicable approved planned-unit-development plans and public plat conditions remain relevant to the particular property.

• Floodplain and regulated-drain approvals: A Floodplain Development Permit is required before covered development in a special flood hazard area. The local definition of development expressly includes walls and fences. State floodway authorization and written drainage-board consent for permanent structures in a regulated-drain right-of-way are separate requirements when their conditions apply.

• Grading and construction stormwater: UDO Section 10.16 requires grading/land-disturbance approval for development disturbing more than one-half acre. Its stated exemptions cover immediate emergency protection; qualifying agricultural land management; additions or modifications to existing detached single-family dwellings; and development disturbing no more than one-half acre. Contiguous subdivided or multiple-owner properties cannot use the last exemption to divide a covered disturbance, and small-site sediment or water pollution remains regulated.

• Half-acre to less-than-one-acre sites: Current Code Sections 14.30.030 and 14.30.040 define a minor construction site as disturbance of at least one-half acre but less than one acre. An individual lot in that range requires a Grading/Land Disturbance Permit application before a building permit. Independent minor sites submit the application; minor sites within a larger common development follow the applicable approved construction plan. The form requests site and disturbed acreage, added impervious area, construction dates and a sketch of discharge points and erosion controls. The published grading permit fee is no charge.

• One-acre and larger construction sites: A major construction site disturbs at least one acre. Submit a construction plan in quadruplicate to the City Engineer or Storm Water Coordinator. A Notice of Plan Sufficiency is required before construction and accompanies the Notice of Intent submitted to the Indiana Department of Environmental Management at least 48 hours before major-site construction. The code’s major-site review fees are $250 for one to five acres and $500 for more than five acres. These provisions apply according to the covered site’s disturbed area and larger-common-development status.

• Public-street excavation and City-drain connections: Cutting, tunneling or excavating in a street, alley or other public place requires the applicable permit, with application at least two working days beforehand. Insurance is required, and a bond may be required. The ROW application includes a location/dimension/depth sketch and any necessary street-closing permission; the published form expires 90 days after City Engineer acceptance. Current code fees are $9.79 per square foot of covered pavement trench, excluding sidewalks/driveways, and $4.54 per square foot for an improper-backfill revisit. The invoice is due within 30 days. Cutting into or connecting to a City drainage structure requires a Storm Water Drainage Permit filed at least 48 hours before excavation/connection. The Street Department requires at least 24 hours to schedule the drainage inspection; changes to the drainage plan require a revision. These local notices are separate from Indiana 811.

FENCE PLACEMENT RULES

• Property-line setback: UDO Section 7.14(B)(4) requires fences at least two feet from property lines in all zones except A1 and A2 Agriculture. A property boundary, building setback line, easement and road right-of-way are different features. The fence application requires their locations and the proposed fence’s boundary distances. Plats, deeds and any required survey establish the applicable boundary information; a curb, ditch, existing fence or GIS display alone does not establish the legal line.

• Rights-of-way, easements, buffers and sight areas: Fences and walls may not occupy or encroach on public rights-of-way, cross public or private easements, or occupy a required buffer yard unless the UDO specifically requires or permits that location. Fence and wall construction within the required sight triangle is prohibited. Section 4.17 also expressly includes fences and walls in its easement-location restriction. The application identifies public utility/drainage easements as areas that must retain their drainage slope and remain free of structures, fences and landscaping, including temporary installations.

• Residential design placement: For housing subject to UDO Section 7.18(A), the RR, R1, R2 and R3 fence standards require at least five feet from the right-of-way and ten feet from the primary facade, enough space to maintain both sides, and no easement location. Section 7.18 applies to new single-family detached/attached and two-family housing and existing residential buildings expanded or altered by more than 50 percent of gross assessed value. Its corner street-side openness and chain-link conditions also apply within that stated design scope.

• Public subdivision easements: Under UDO Section 9.14, utility easements must be enforceable, binding and recorded on the secondary plat. Easements adjacent and parallel to street ROW have a minimum width of 15 feet; those not along streets have a minimum width of 20 feet and may be divided along a shared lot line. Required subdivision drainage easements are at least 20 feet wide; watercourses can require additional areas for drainage improvement/protection. Regulated-drain easements follow Indiana drain law, and maintenance easements may be required for dams or adjoining property. The plat’s actual easement location controls the available fence area.

• Regulated-drain corridors: IC 36-9-27-33 provides a corridor extending up to 75 feet, measured at right angles from a tiled drain’s centerline or the top edge of each bank of an open regulated drain, as determined by the surveyor. Permanent structures require written drainage-board consent. Temporary structures must be removed immediately when ordered; planting trees, shrubs or woody vegetation also requires written consent. Qualifying new drains established after September 1, 1984 and urban drains may have board-approved reductions to at least 25 feet from each open bank or 15 feet from a tiled centerline. In a platted subdivision, a further tiled-drain reduction requires the surveyor’s recommendation and cannot be less than seven feet on each side or less than that recommendation. Existing qualifying utility use is protected when a corridor is reduced. Private/mutual drains and ordinary ditches have different statutory status; municipal transfers of drain jurisdiction can also affect the responsible authority.

• City drainage and gas access: Drainage easements provide inspection and maintenance access, and drainage channels must remain unobstructed. A fence that cuts into or connects to a City culvert, storm sewer, curb, gutter, street or paved ditch involves the separate drainage-permit rules. For City gas customers, the gas line, meter and appurtenances must remain accessible 24 hours a day, seven days a week. A customer who fences or gates the property must make all-hours access arrangements satisfactory to the Gas Manager. Obstructions are prohibited and may require immediate removal or service interruption.

• Floodplain and floodway property: Code Chapter 17.10 treats fence/wall erection as development and includes wire fences and debris-catching materials within its obstruction definition. Covered SFHA development needs local floodplain approval. The ordinance also addresses known flood-prone areas and discrepancies between mapped boundaries and actual natural grade. The Director of Community Development and Planning administers the local permit. Plans identify the project, legal description, location, dimensions, grades and drainage; watercourse alteration/relocation can require hydraulic/hydrologic study, DNR approval and FEMA map-revision procedures.

• Floodway and undelineated flood areas: For nonexempt development in an identified floodway, state authorization precedes the local approval. Local standards prohibit development adversely affecting floodway efficiency/capacity, using the stated 0.15-foot regulatory-flood increase comparison. Identified fringe follows the local permit branch. Where floodway/fringe limits are undetermined, the ordinance has a DNR review/assessment branch for upstream drainage greater than one square mile, and an engineering-analysis branch for drainage less than one square mile; the latter limits cumulative increase to 0.14 foot and prohibits increased flood damage. These site branches apply to the covered development. Building-floor elevation and floodproofing documentation apply to the building conditions specified in the code.

• Qualifying agricultural fences in a floodway: Indiana’s statutory state-permit exemption covers an agricultural fence primarily keeping animals in or out that does not obstruct water or debris flow through a floodway. Local floodplain development requirements remain separate. State floodway licensing also has a separate fringe treatment. Ordinary privacy-fence work follows its actual floodway/development conditions.

• Construction erosion controls: An individual lot disturbing less than one-half acre in the specified unplatted/existing-subdivision setting outside a regulated project needs no individual Notice of Intent or construction plan under Code Section 14.30.120, but its applicable erosion controls remain. These include stable construction access, perimeter controls before disturbance, minimizing sediment/tracking, road cleanup without flushing, restoration/stabilization of damaged adjacent ground, and final stabilization. Larger common plans and regulated individual lots have their own construction-plan obligations. Project disturbance calculations include common improvements and owner-controlled off-site work; the single-family project calculation uses one-half acre expected disturbance for lots at least that size and the entire lot for smaller lots.

• Postconstruction stormwater scope: Code Section 14.40.030 generally covers development/redevelopment disturbing over one acre, with stated exceptions for projects adding no final impervious surface; qualifying unimproved strip development outside a larger plan; individual residential lots within permitted projects; residential developments of four or fewer lots with impervious surfaces no more than ten percent of project acreage; single-family residences/private ponds outside larger common plans; cultivation; and agricultural conservation practices. The City Engineer administers this chapter.

• Indiana 811 before covered post-hole digging: Submit an Indiana 811 locate notice at least two full working days and no more than ten calendar days before covered work. A working day is 7 a.m.–6 p.m. Indianapolis time, excluding Saturdays, Sundays and state/national legal holidays. Normal work starts no earlier than 7 a.m. on the next working day after the two full working days following receipt; the earlier-start exception requires all affected operators’ electronic positive responses showing marked facilities or no facilities. Check responses and markings and affirmatively acknowledge the required operator information to Indiana 811 before starting. Notice expires at 11:59 p.m. Indianapolis time 20 days after its receipt date; unfinished excavation requires a new request/notice and renewed operator markings before continuing. The hand-tool exception requires solely hand tools, property owned or controlled by the person digging, and depth no greater than 12 inches.

• Digging near marked utilities: Maintain the statutory equipment clearance/tolerance zone, which includes the plant width plus at least two feet around its outer limits. Specified close-clearance or hard-surface exposures use hand, air, vacuum or hydro-vacuum methods. Mechanized work within the zone requires precise visual location or confirmation of no facility to excavation depth, support/coating precautions and a separate visual monitor; initial hard-surface removal has its own limited exception. Report unmarked-facility evidence or illegible markings to Indiana 811. Utility locating does not replace Jasper approvals or property restrictions.

FENCE HEIGHT AND VISIBILITY RULES

For residential uses, UDO Section 7.14 establishes these maximums:

• Front yard: four feet.

• Side yard: six feet.

• Rear yard: eight feet.

• Corner lots: both street-front yards are front yards and have the four-foot front-yard limit.

• Through lots: the yard facing the primary structure’s front is the front yard; the opposite technical front yard is treated as a rear yard for this height rule.

Height is measured from adjacent grade, including the base of a berm, to the top of the fence. For housing subject to the Section 7.18 residential design standards, a corner street-side fence must also be at least 50 percent open. In the Mixed-Use Overlay, a retaining wall adjacent to a public-street sidewalk may not exceed two feet.

• Street and alley sight triangles: The required area is bounded by the street ROW lines and the diagonal connecting points measured 25 feet along the ROW for a local street/alley, or 35 feet for a collector or arterial street. A rounded or cut corner uses the extended ROW intersection. Fences and walls cannot occupy the required triangle.

• At-grade railroad crossings: The triangle uses the lot line along railroad ROW, street ROW, and the diagonal connecting points 25 feet from their intersection.

• Driveway-related branch: On a non-single-family-zoned lot adjacent to a lot with a driveway, Section 7.2(D) uses the street ROW, driveway surface edge, a point ten feet along the driveway from ROW, and the applicable street ROW distance. The ordinance’s illustration also depicts a ten-foot-by-ten-foot driveway triangle.

• Clear-vision height band and B2 buildings: Within sight triangles, nothing may impede vision between 2.5 and ten feet above intersecting centerline grades. The current provision states this for all zones; its B2 exception concerns buildings erected according to established setbacks. Fence-specific sight-area restrictions continue separately.

• Qualifying live boundary hedges: IC 32-26-5 requires a hedge or other live fence along a dividing property line to be cut and trimmed at least once each calendar year to no more than five feet high and three feet wide. A qualifying written complaint leads to trustee examination within five days and, where required, notice allowing 30 days to trim and remove brush. This is the live-boundary-fence framework.

• Spite-fence nuisance: Under IC 32-26-10, a fence-like structure unnecessarily exceeding six feet that is maliciously erected or maintained to annoy an adjoining owner or occupant is a nuisance. The malicious-purpose and unnecessary-height elements are part of this separate rule.

MATERIAL AND CONSTRUCTION LIMITS

• Wood: The City’s fence application expressly lists wood. Yard, height, structural orientation, pool use and applicable overlay/design standards govern the proposed installation.

• Vinyl/PVC: The application expressly lists vinyl but does not separately name PVC. The Mixed-Use Overlay’s historically appropriate front-fence requirement and other location/design conditions still apply to the project.

• Chain-link and flexible wire: The application recognizes chain-link, but residential front yards prohibit chain-link and similar flexible or rolled woven/welded metal fencing. Solid metal panels with solid, formed joints are excluded from that material prohibition. Housing subject to Section 7.18 also prohibits chain-link in the front and street-side yard. In the Mixed-Use Overlay, chain-link is prohibited except where it is not visible from a public street.

• Dangerous/sharp materials: Chicken wire, concertina wire, razor wire, razored edges, broken glass, affixed spikes, projecting nails and other pointed instruments are prohibited unless expressly permitted by the section. Decorative spikes integral to an ornamental fence are permitted.

• Electric and barbed wire: These are prohibited on residential property except in an agricultural zoning district. The Mixed-Use Overlay separately prohibits barbed wire. Residential use and the property’s actual district determine the applicable branch.

• Structural orientation: Structural members, braces, bolts and the structural side must face the interior of the enclosed property.

• Mixed-Use Overlay walls and front fences: Front-yard fencing must be historically appropriate. A retaining wall alongside a sidewalk on a public street has the two-foot height limit and must use split-face or textured-finish concrete block faced with stone, brick or stucco.

• Covered trash/recycling/storage enclosures: UDO Section 7.13 requires its outdoor receptacle/dumpster/compactor enclosures on an improved surface, screened on all sides with wood, brick, stone or exterior-building materials similar to the principal structure. At least one side has a movable access gate. Enclosures are at least six feet high and tall enough to conceal contents from adjacent parcels/public ROW; they follow applicable lot setbacks, cannot occupy front or side yards, and must remain in good repair. Where the district permits outdoor equipment/scrap/material storage under Section 7.13, its enclosure must be an opaque fence/wall at least six feet high and high enough to conceal the contents, while complying with Section 7.14.

• Required development screens and landscape maintenance: Where dissimilar districts/uses require a public buffer, the Commission may require a wall, fence or greenbelt and may waive it where equivalent existing/planned parks, recreation areas, topography or natural screening serves that purpose. Existing adjacent owners need not participate in installing the buffer; it is completed before occupancy and maintained by the property holder. Required landscape materials cannot occupy easements, ROW or septic fields. At least 50 percent of required screening plant material must be evergreen, with year-round distribution and groundcover on unplanted portions. Project landscape fences/walls must remain in good repair and free of refuse. Required dead plants are replaced within 180 days, subject to weather extension; required opacity/growth must be maintained, and a required continuous solid planting screen must form within three years.

• Fence condition: Code Section 7.24.030 includes fences in the property’s unsafe, unsanitary and nuisance-condition requirements. Property must remain safe and avoid unlawful obstruction of streets, easements and other covered public areas.

• Jasper private-pool enclosures: Code Section 7.26 applies to the specified outdoor private residential pools deeper than 42 inches, serving one- or two-family household/guest use without profit. Its in-ground enclosure rule limits openings to four inches except gates/doors, prohibits configurations with child-climbable handholds or footholds, and requires fences/gates at least four feet above walk grade. Entry points are gated; gates/doors have self-closing and self-latching devices at the top inaccessible to small children.

• Jasper pool exceptions: Hot tubs/spas need no fence if covered by a heavy, permanent, tight cover secured so a small child cannot open/remove it. Above-ground pools need no separate fence when sidewalls are at least four feet high or a fence atop the walls reaches four feet from ground. A temporary above-ground pool installed no more than 48 hours also has a local enclosure exception. The local code separately states that a pool cover does not replace a fence.

• Indiana residential-pool access methods: The Indiana Residential Code’s replacement Section R326 covers qualifying residential in/on-ground pools capable of depth greater than 42 inches and indoor residential pools regardless of depth, for the stated noncommercial use by no more than two owner families and guests. Artificial lakes are excluded. Its access-control choices include: a wall/fence at least four feet high surrounding the pool and deck with self-closing/latching gates and doors capable of locking; another at-least-four-foot means deemed impenetrable by the enforcing authority at construction and surrounding the unused pool/deck; or a combination with the specified gate/door conditions.

• State power-cover option and Jasper’s different cover rule: Indiana R326.27.3 also allows a power safety cover continuously connected to the deck to prevent access when closed, mechanically operated by a key, key-and-switch or personal-code touchpad, installed with the manufacturer-required tracks/rollers/rails/guides, and bearing identification for ASTM F 1346-91 (2018) power-cover compliance. Jasper’s local code says covers do not replace fencing. A cover-based or above-ground-wall access arrangement therefore presents different published state and local conditions; confirm the applicable method with the Community Development & Planning Department before relying on an alternative to enclosure fencing.

• Classified-animal enclosures: Code Section 6.01.160 provides indoor confinement or a locked fenced rear-yard portion for a nuisance animal, and indoor confinement or an escape-proof enclosure for a dangerous/vicious animal. An escape-proof enclosure has a secure bottom or concrete/cement floor and sufficient height to prevent the animal jumping out unless securely roofed. If the animal escapes, a five-sided enclosure on concrete is required. All such fencing must conform to City fence standards.

• Qualifying agricultural partition boundaries: IC 32-26-9 applies only where at least one adjoining parcel is agricultural land—zoned/designated agricultural, used for crops/livestock or reserved for conservation—and the statutory outside/abutting/adjacent municipal-boundary conditions apply. Its lawful-partition specifications include sufficiently tight/strong four-foot straight board/wire/picket fences, four-and-one-half-foot straight rail fences or five-foot worm rail fences for the listed livestock. For a north–south line the east owner ordinarily builds the north half and west owner the south half; for an east–west line the north owner ordinarily builds the west half and south owner the east half. A qualifying different half maintained at least five years can continue. The statute has proportional-cost and 20-day notice/trustee procedures, practical near-boundary placement where a creek prevents a line fence, and swing-up floodgate alternatives where stationary watercourse fencing is impracticable. Watercourse allocation disputes have the stated three-person apportionment process. These agricultural boundary obligations operate within their statutory setting.

PRIVATE RESTRICTIONS

HOA and private subdivision covenants, deed restrictions, private architectural-review requirements, recorded private easements, conservation easements, agricultural agreements and private boundary agreements may impose additional height, material, location or approval conditions. City approval does not replace those instruments.

UDO Section 9.1(F) preserves private easements, covenants and agreements, and does not obligate the City or Plan Commission to enforce them. IC 32-26-3-1 requires adjoining owners choosing a fence arrangement different from the article’s framework to use a signed written agreement recorded in the county or counties where the properties lie. The particular recorded instrument determines its private conditions.

REVIEW AND ENFORCEMENT CONTEXT

Fence issues are typically reviewed during permit or approval review when required, and through complaint-based code enforcement. Examples include:

• Fence permit and site-plan review: Checking the proposed location, height, lot/frontage classification, materials, required setback measurements, survey staking and consistency with the approved plan. The City’s process includes site checks and notice when completed work differs from the approval.

• Visibility and public-access review: Addressing sight triangles, street-front height, ROW encroachments, easement obstruction, public excavation and required utility access.

• Design and development conditions: Applying the property’s Mixed-Use Overlay, scoped residential design standards, approved development/plat conditions and required landscape-screen maintenance. The Board of Zoning Appeals has the City’s variance/appeal role; a Zoning Compliance Letter is a separate dated determination.

• Pool and animal enclosures: Applying the relevant pool-opening, climbability, gate/cover and confinement conditions. The differing state/local pool alternatives need attention when the project relies on a cover or above-ground wall instead of a separate enclosure.

• Drainage, floodplain and digging: Reviewing covered floodplain development, nonexempt state floodway work, regulated-drain consent, City-drain connections, construction stormwater controls and Indiana 811 duties.

• Condition and nuisance: Addressing unsafe or deteriorated fence conditions and separately applicable live-boundary-hedge or spite-fence issues. UDO enforcement includes written stop-work orders for required approvals not obtained, violations or inconsistent construction.

USING THIS INFORMATION

This page provides general orientation on how residential fence rules are structured and applied within the City of Jasper, Indiana. Updated October 2026.

In addition to local fence rules, certain Indiana laws apply statewide. See Statewide Fence Laws in Indiana.

It is not legal advice and does not replace official ordinances, permits, certificates, improvement-location approvals, development approvals, applicable building-code requirements, surveys, or professional guidance. Rules and interpretations may change, and application may vary based on zoning district, plan-commission jurisdiction, county zoning coverage, site conditions, subdivision/land-development status, easements, rights-of-way, floodplain or floodway status, stream conditions, stormwater or drainage requirements, regulated-drain conditions, road or highway conditions, INDOT jurisdiction, historic/design/special-district status, rural or agricultural context, livestock, lawful-fence or agricultural partition-fence context, live-fence or spite-fence conditions, local permit administration, pool-barrier use, Indiana 811 utility-excavation requirements, and private restrictions such as HOA covenants, deed restrictions, private agreements, recorded partition-fence agreements, or conservation easements. Before purchasing materials or beginning construction, confirm current requirements and site-specific limitations with the Community Development & Planning Department and any applicable private agreements. If this page conflicts with official ordinances, published guidance, adopted district guidelines, or direction from the Community Development & Planning Department, the official sources control. For legal advice or legal interpretation, consult a licensed attorney.