FENCE RULES – BREMEN (CITY), GEORGIA

OVERVIEW

This page applies to residential fence work within the municipal limits of the City of Bremen, including its portions in Haralson and Carroll Counties. For property in the counties’ unincorporated areas, see Haralson County fence rules or Carroll County fence rules, as appropriate to the property’s location.

Bremen requires a city permit for fences and distinguishes open front-yard fencing from solid side and rear fencing. In residential zones, front fences are limited to 3.5 feet and must be open; solid fences beside or behind residential structures may reach six feet. Wood picket and ornamental front fences are recognized, chain-link is prohibited in residential front yards, and vinyl/PVC is not specifically addressed. Property lines, multiple street frontages, visibility, utility access, planned developments, flood conditions, environmental buffers and pool barriers can change the applicable requirements. Updated October 2026.

Quick questionBremen answer
Permit or approvalA city fence permit is required. Section 110-74 requires an application, permit and application fee. Separate site-condition approvals may also apply.
Typical fence heightIn residential zones: 3.5 feet for open front-yard fences; six feet for solid fences at the rear and side of residential structures. Visibility and special-site rules also apply.
Placement & property linesThe code expressly allows perimeter fences and walls on a property line and excludes fences from its five-foot accessory-structure setback. Street rights-of-way, visibility, easements, buffers, drainage and service access remain separate constraints.
Common fence materialsWood: open wood picket is expressly recognized for front yards. Vinyl/PVC: not specifically addressed as an ordinary fence material. Chain-link: prohibited in the front yard of any residential structure.
Important local conditionsFence rules may be further affected by multiple street frontages, intersection and driveway visibility, public rights-of-way, utility access and easements, planned developments, subdivision buffers, floodplain and floodway conditions, wetlands and water-supply buffers, nonexempt land disturbance, pool barriers, and qualifying Estate Residential animal enclosures.
Official local resourceCity of Bremen Planning & Zoning

The table above is for quick reference. Additional fence-rule details appear in the corresponding sections below. Before purchasing materials or beginning construction, read the sections that apply to the property, review the linked official sources, and confirm site-specific questions with the City of Bremen codes enforcement officer or the responsible office identified for that issue.

GOVERNANCE

The City of Bremen adopts its municipal fence requirements through the Bremen Code of Ordinances and Land Development Code. Section 110-74 contains the principal fence rules. The Land Development Code is administered and enforced, unless otherwise provided, by the city manager and/or codes enforcement officer. The zoning officer is the officer designated by the city manager to administer the code and issue zoning permits. The Planning & Zoning Commission and Board of Development Appeals have separate planning, review and appeal functions.

Fence regulation also involves other city responsibilities. Public Works administers city right-of-way work. The city manager or designee administers flood-damage prevention, with floodplain applications submitted through the city department of community development. The building inspector administers wetlands protection and the water-supply-watershed review procedures. The arborist reviews required landscaping and screening. Bremen is listed as a local issuing authority for erosion and sedimentation control; covered disturbance involves the city and the applicable soil and water conservation review process.

Georgia’s mandatory construction-code framework also applies. The applicable statewide cycle includes the 2024 International Residential Code, International Building Code, and International Swimming Pool and Spa Code with 2026 Georgia amendments, effective January 1, 2026. The Georgia Department of Community Affairs construction-code page provides the adopted editions and amendment packets. Pool-barrier standards are a separate subject from ordinary yard-fence heights and the city fence permit.

Under Sections 100-4 and 100-5, specific Land Development Code requirements govern conflicting general provisions, and the more stringent requirement governs other conflicts. Public easements and applicable private agreements also remain relevant. Municipal requirements apply inside Bremen; the counties’ unincorporated-area rules have their own territorial scope.

PERMIT AND APPROVAL REQUIREMENTS

• City fence permit: Section 110-74 requires application to the city, issuance of a permit and payment of the application fee before a fence is erected. The City’s published construction and development fee schedule lists a $25 walls/fences permit fee under Section 110-74. Confirm the applicable fee when applying.

• Application and plans: Unless otherwise provided, Section 100-8 directs permit and administrative applications to the codes enforcement officer with a completed, signed and verified application, fee, and two copies of scaled plans. Plans show actual lot dimensions, existing improvements, the proposed improvement’s shape, size, height, use and location, setback lines and buffers, together with other necessary compliance information.

• Applicable site-plan information: The code’s list includes project name, owner/address, date, scale, north arrow, vicinity map, adjacent ownership and zoning, boundaries, acreage, proposed use, dimensioned yards, buildings and floor areas, existing/future street rights-of-way and pavement widths, driveway dimensions and distance to the nearest intersection, parking/loading/walkways, buffers and plant schedules, dumpster location, 100-year floodplain elevations, sewer/septic connections and the nearest fire hydrant. Topographic contours are at five-foot intervals for property greater than one acre and two-foot intervals for property less than one acre. These listed items apply where relevant to the project; the city may require other information necessary to evaluate it. Section 100-13 requires payment of all applicable fees, charges and expenses before action on an application or appeal.

• Administrative review and duration: Where no public hearing is required, Section 100-8 allows a reasonable staff-review period of no more than 30 days; denial must state the reasons in writing. Approved design and construction standards apply to the project for 24 months, after which later work follows then-current requirements. Under Section 100-14, an approval generally expires if substantial construction progress has not occurred within 12 months; a new application, approval and fee are then required.

• Variance and appeal: Section 100-16 provides a Board of Development Appeals hardship-variance process. Relief requires the specified hardship and property-condition findings, protection of public safety and welfare, and no substantial public detriment or impairment of the regulation’s purpose. The listed conditions concern exceptional size, shape or topography, unnecessary hardship, conditions peculiar to the property, and conditions not caused by the owner. Administrative appeals under Section 100-17 must be filed with the city clerk within 30 days after notice of the adverse decision. Section 100-19 separately specifies a 30-day period for appeal of a board decision to the appropriate superior court.

• Planned unit developments: A property within a planned unit development is also subject to its approved plans and Chapter 114. Changes to an approved development plan require Planning & Zoning Commission review and mayor/city council approval. Section 114-177 requires the documents needed to demonstrate compliance for construction within a PUD.

• Floodplain development: Chapter 108 requires a development permit before covered development in a special-flood-hazard area. Its definition includes manmade changes such as excavation, fill, grading and drilling. Applications go to the city department of community development with duplicate scaled plans showing the proposed work, elevations, fill, equipment/material storage, drainage and any proposed watercourse alteration. The floodplain administrator is the city manager or designee.

• Wetlands: Section 106-21 requires written city permission or a permit for regulated activity in the wetlands protection district. Regulated activity concerns dredged or fill material discharged into waters of the United States, subject to the stated federal exceptions. If proposed development lies within 50 feet of the mapped district boundary, the specified Corps of Engineers determination is required. Where jurisdictional wetlands are present, the required Section 404 permit or letter of permission must precede local permission.

• Wetland application details: The building inspector administers this process. Site plans use a scale of at least one inch to 50 feet and show excavation/fill volumes and cross sections, wetland boundaries, impervious surfaces on the site and within 100 feet, distance to affected waters, site/adjacent elevations within 200 feet, spill controls and temporary hydrologic changes. Contour intervals may not exceed two feet, or one foot where slopes are two percent or less. The code provides up to a $100 evaluation fee, a 30-day complete-application review, and expiration after 12 months without commencement or after a 12-month suspension/abandonment. Section 106-22 permits a compliance bond of $1,000.

• Water-supply-watershed review: For a local development-permit application in the named Tallapoosa River, Beach Creek and Lake Tisinger watershed districts, Section 106-63 requires a site plan at one inch to 50 feet, identifying excavation/fill and cross sections, wetlands, impervious surfaces on the site and within 200 feet, distance to affected waters, spill controls and hydrologic changes. Elevations within 200 feet use contours no greater than two feet, or one foot on slopes of two percent or less. Detailed-plan exceptions include the specified detached homes in subdivisions of fewer than five parcels, repairs to previously approved facilities and construction of minor structures such as sheds or residence additions. Applications are reviewed by the building inspector within 15 days, with an evaluation fee up to $100; significant site-plan changes require approval. Permit expiration is specified after 12 months without commencement or following suspension/abandonment.

• Minor fence-post disturbance: Section 118-3(3) exempts fences and related minor land-disturbing activities that result in minor soil erosion from the local erosion-control chapter.

• Nonexempt land disturbance: Covered work outside that exemption requires a city land-disturbance permit, applicable EPD notice, erosion/sedimentation/pollution-control plans and fees. Section 118-5 specifies five copies of the plans and site-visit certification by the plan preparer or designee. District plan review generally has a 35-day period, subject to an authorized local-review agreement; required buffer variances, fees and any bond precede permit issuance. Section 118-5(d) specifies issuance or denial within 45 days after receipt of a complete application, subject to the stated prerequisites, and separate permits for development phases. A bond may be required up to $3,000 per acre or fraction. The fee schedule lists the state-assessed fee at a maximum of $80 per disturbed acre, while separately listing applicable local disturbance charges. These processes concern nonexempt disturbance.

• Right-of-way work: Chapter 20 requires an approved encroachment application and plans for covered excavation or construction in city rights-of-way, with the permit kept onsite. Public Works reviews this work. Permanent fences remain prohibited in street rights-of-way.

FENCE PLACEMENT RULES

• Private property lines: Section 100-6 expressly includes perimeter fences and walls among accessory uses that may be located on the property line. Section 110-75 excludes fences from the five-foot property-line setback stated for accessory uses or structures of 200 square feet or less. A property line is distinct from an easement, environmental buffer, zoning yard or public right-of-way. Surveys and recorded instruments establish boundaries and property interests; existing fences, curbs, ditches, hedges and GIS lines alone do not establish the legal boundary.

• Street yards and multiple frontages: The front yard extends between the nearest street right-of-way and the front building line projected to the side lot lines. Side and rear yards follow the code’s separate definitions. Section 110-79 requires a minimum front yard for each street frontage on lots abutting more than one street.

• Public rights-of-way: Section 20-3(c) prohibits permanent features, expressly including fences, within the street right-of-way. Public Works may remove obstructions affecting clear vision or pedestrian movement in its street/sidewalk maintenance work.

• Service access and parking: Section 110-74 requires access for garbage collection, water and other utility meters, and mail delivery. Fences cannot interfere with required off-street parking. In non-PUD townhouse developments, side/rear privacy fences must preserve personnel and equipment movement to interior units for maintenance, emergency access, sanitation and utility service.

• Subdivision utility and drainage easements: Section 120-67 requires easements for utilities and related structures outside the right-of-way, extending at least ten feet beyond their outermost part and totaling at least 20 feet wide. The actual recorded easement and required access affect a proposed fence location.

• Subdivision screening buffers: Section 120-68 requires buffers between specified incompatible developments and, in certain cases, requires proposed residential development to provide a buffer where an adjoining preexisting incompatible use lacks one. Required buffers are designated on plats as permanent undisturbed buffer easements. A wall or fence may be constructed within a buffer, but the section’s disturbance and approval requirements also apply. The Planning & Zoning Commission may require additional planting, a wall, fence or berm to achieve screening. Buffer areas adjacent to state waterways permit only hand clearing subject to applicable state/federal requirements.

• Subdivision watercourse buffers: Section 120-69(a)(4) requires an undisturbed natural vegetative buffer at least 25 feet from the top of stream bank where a subdivision is traversed by a watercourse, drainageway, natural channel or stream. The section also provides for additional width needed for future construction and refers to Carroll County Code Enforcement for those additional widths.

• Buffers across a two-lane road: Where covered nonresidential or multifamily property faces a single-family residential district across the same two-lane public road, Section 120-68(e) specifies undisturbed buffers according to right-of-way width: 20 feet for ROW up to 50 feet; 15 feet for ROW of 51–60 feet; and ten feet for ROW over 60 feet. The stated disturbance allowance is for curb cuts, required sight distance and access, with suitable tree/shrub landscaping.

• Floodplain and floodway: Section 110-47 permits floodplain fences with enough open area for water and debris to pass freely. Structures or flow obstructions below the 100-year flood elevation require the specified compensating flow-area/storage plan. Under Section 108-78(4), regulatory-floodway encroachments require hydrologic/hydraulic analysis and registered-professional-engineer certification demonstrating no increase in flood levels or floodway widths. In the special-flood-hazard settings described by Section 108-79, subsection (2) addresses encroachments including structures or fill material, and applies only when the administrator cannot obtain the specified base-flood-elevation or floodway data from available sources. For a project proposing such a covered encroachment within the stream width or 20 feet, whichever is greater, measured from the top of bank, the section requires registered-professional-engineer certification demonstrating a flood-level increase of no more than one foot during the base flood discharge.

• Water-supply stream corridors: In the Beach Creek, Lake Tisinger and Bush Creek small water-supply watersheds, Section 106-61 establishes a 100-foot vegetated buffer and 150-foot impervious-surface setback on each side of perennial streams within a seven-mile radius upstream of the intake or reservoir. Outside that radius, the respective distances are 50 feet and 75 feet. Distances are measured from stream banks. These watershed provisions also limit aggregate impervious coverage to 25 percent or existing use, whichever is greater. Listed exemptions include land uses existing before adoption and qualifying utility, forestry and agricultural activities.

• Reservoir shore buffers: Section 106-61 establishes a 150-foot buffer from the reservoir boundary at both Lake Tisinger and Bush Creek. The reservoir boundary is defined by normal pool level. Lake Tisinger is owned/protected by the City of Bowdon; Bush Creek is owned/protected by the City of Bremen. Stream-corridor and reservoir-buffer requirements are separate site conditions.

• Groundwater-recharge areas: Chapter 106 contains additional development/site-plan procedures for mapped groundwater-recharge districts. For covered permit applications, Section 106-90 specifies a one-inch-to-50-foot plan; excavation/fill and cross sections; wetlands; impervious surfaces and elevations on/within 200 feet; waterbody distances; spill controls; and hydrologic changes. Contours are no greater than two feet, or one foot for slopes of two percent or less. The stated detached-home, repair and minor-structure detailed-plan exceptions apply. The building official handles this review, with the specified 15-day review, 30-day deemed-approval provision and up-to-$100 evaluation fee for covered applications.

• Erosion and larger projects: In addition to the minor-erosion fence exemption, Section 118-3 contains a separate exemption for projects disturbing less than one acre, with exceptions for larger common development plans and work within 200 feet of the stated state waters. Sediment must be kept within the property for the specified smaller projects near otherwise excluded drainage channels. Nonexempt disturbance is subject to erosion-control measures, applicable stream buffers and permit conditions.

• Erosion-control stream buffers: For work subject to Section 118-4(c), the buffer is generally 25 feet along state waters and 50 feet along classified trout waters, measured horizontally from the point where normal stream flow or wave action has wrested vegetation. The stated drainage-structure, roadway-drainage and authorized-variance provisions apply. The 25-foot provision also excepts ephemeral streams meeting all of its criteria: short-duration flow after precipitation, a channel above the groundwater table year-round, no groundwater source, and precipitation runoff as the primary flow source. For small trout springs/streams averaging 25 gallons per minute or less, the code provides a 25-foot buffer or piping under the applicable general-variance rule and notice/method requirements; piping must stop short of downstream property and preserve applicable adjacent-stream buffers. Covered buffers remain undisturbed during construction. After final stabilization, the stated trimming/thinning allowance requires protective cover and sufficient natural canopy; qualifying owner-occupied single-family construction has the specified earlier trimming allowance.

• Georgia 811 before fence-post digging: Contact Georgia 811 before digging. Georgia law covers excavation with mechanized equipment, including powered post-hole equipment; Georgia 811 recommends its free public-utility locate service for manual digging as well. Its published safe-digging guidance instructs users to submit a ticket at least three business days before excavation. The statutory notice period runs from 7 a.m. on the next business day and allows the prescribed two-to-eight-business-day interval. Check the ticket’s effective date, utility responses and markings before work; work under a locate request cannot extend beyond 30 calendar days after its effective date without the required renewed notice.

• Overhead high-voltage lines—covered trade or business work: For covered fence work performed in pursuit of a trade or business, including contractor work, Georgia’s High-voltage Safety Act applies where a person, tools, machinery, equipment or materials may come within ten feet of an above-ground electric line carrying more than 750 volts between conductors or from a conductor to ground. The person responsible for the work must notify Georgia 811 at least 72 hours before work, excluding weekends and holidays. Protective arrangements with the line owner/operator and the required safety measures must be completed before work begins. Those measures include the utility’s selected feasible safeguard: de-energizing and grounding, relocation, or protective covering or mechanical barriers.

FENCE HEIGHT AND VISIBILITY RULES

• Front yards in residential zones: Section 110-74 limits front-yard fences to 3.5 feet and requires open-space construction such as traditional open wood picket or ornamental fencing. Section 110-31 also permits ornamental front fences at that height, subject to design and sight-line requirements.

• Solid side and rear fences in residential zones: Section 110-74 permits solid fences no more than six feet high at the rear and side of residential structures.

• Height measurement: The ordinary fence provisions do not specify a separate fence-height measurement method or an additional allowance for posts, caps or a retaining-wall combination.

• Intersection visibility: Under Section 110-76, a fence, wall or other vision obstruction between three and 15 feet high is prohibited within 20 feet of the intersection of the right-of-way lines of streets, roads, highways or railroads. The stated exceptions are utility poles, light or street-sign standards, tree trunks and presently existing Central Business District structures. Fence location must also preserve adjoining owners’ traffic views when entering/leaving a street or public way.

• Development-entrance sight distances: Section 104-19(j) measures horizontal sight distance along the existing pavement edge from the entrance centerline to the projected sight line’s intersection with the pavement, using visibility two feet above the road surface. Near a crest, vertical sight distance is measured along the roadway using a four-foot driver eye and a six-inch object at the entrance centerline. Minimum horizontal/vertical distances in feet are 150/200 at 25 mph; 200/200 at 30 mph; 250/250 at 35 mph; 325/300 at 40 mph; 400/400 at 45 mph; 475/475 at 50 mph; and 550/550 at 55 mph.

• Pool and spa barriers: Where a barrier is required under ISPSC Section 305, its top must be at least 48 inches above outside grade around the entire perimeter and for a horizontal distance of three feet outside the barrier. Maximum bottom clearance is two inches over nonsolid grade such as grass/gravel and four inches over a solid surface, measured on the side away from the pool. A barrier mounted on the pool/spa top may have no more than four inches between that top and the barrier bottom.

• Permanent detention-pond fencing: Section 104-20(h) specifies a minimum total fence height of seven feet for the designated pond facility. Its construction specifications appear below.

MATERIAL AND CONSTRUCTION LIMITS

• Wood: Traditional open wood picket fencing is expressly recognized for residential front yards, within the 3.5-foot height limit and other applicable conditions.

• Vinyl/PVC: The ordinary residential fence provisions do not specifically address vinyl/PVC fencing.

• Chain-link: Section 110-74 prohibits chain-link fencing in the front yard of any residential structure.

• Planned-development fence and wall design: Section 114-176 requires design compatibility with the main building’s architecture and states that similar materials should be used. Fences/walls 50 feet or longer and four feet or taller should reduce visual monotony through changes in plane, height, material/texture or significant landscape massing. Residential mechanical/electrical equipment must be screened with plants or decorative fencing. PUD retaining walls should have minimized height/length and suitable landscaping; tall smooth-faced concrete retaining walls should be avoided in highly visible areas, with terracing considered as an alternative.

• Required buffer screening: Section 104-102 requires shrubs and/or trees, which may be supplemented by walls, fences or berms. Screening must provide year-round maximum opacity from ground level to at least six feet, screening activity from the normal first-story window level on adjoining property. Alternatives subject to arborist approval include six-foot evergreen shrubs at four-foot centers, tall evergreens with ground-reaching branches, a combination of shrubs at 30-inch centers with small trees at 30-foot centers and large trees at 40-foot centers, or a six-foot masonry wall. Sight-obscuring fencing is identified for a very dense barrier. Required landscape plans identify proposed walls/fences and other improvements and need arborist approval.

• Qualifying parking-lot frontage screening: For parking lots subject to Section 104-95, including lots of five or more spaces, one Section 104-97 option is a three-foot brick, stone, or poured-and-stained concrete fence/wall with a four-foot buffer strip and at least one shade tree per 35 feet of frontage. This is a covered parking-lot landscaping option.

• Fence condition: Section 16-1 includes structurally unsound fences and fencing presenting hazards to children within the nuisance provisions.

• Estate Residential animal enclosures: Under Section 110-32, qualifying livestock/riding-stable uses require at least one acre of fenced area per animal, excluding household pets.

• Permanent detention-pond enclosure: Section 104-20(h) requires complete enclosure with a 12-foot double-leaf gate. The specified minimum seven-foot fence uses two-inch mesh, nine-gauge, 72-inch aluminum-coated steel fabric conforming to ASTM A491, plus seven-gauge aluminum-coated barbed wire with four-point barbs spaced five inches apart on support arms. Galvanized line posts are 2.5 inches O.D., 3.65 lb/ft; corner posts three inches O.D., 5.79 lb/ft; gate posts four inches O.D., 9.11 lb/ft; and top rails 1⅝ inches O.D., 2.27 lb/ft, with extra-long pressed-steel sleeves. Corner/gate posts require struts and tie bracing. Posts are at no more than ten-foot centers, embedded a full three feet in concrete filling the postholes, with grout extending two inches above finished ground. Galvanized gate frames are two inches O.D., 2.75 lb/ft, with welded corners and required bracing/trusses. Gates require heavy-duty latches, keepers and hardened-bronze padlocks with duplicate master keys. Posted pond warning signs are required at the gate and every 50 feet along the outside fence; access is by a 12-foot gravel drive. The required landscape plan screens the facility with evergreens. These specifications apply to the detention facility.

Pool and spa barriers are subject to the following additional construction and access-control standards under ISPSC Section 305 and Georgia amendments:

• Safety covers and permanent-barrier timing: A lockable spa/hot-tub safety cover complying with ASTM F1346, or a powered pool safety cover complying with that standard, provides the stated exception from Sections 305.2–305.7. Without a qualifying safety cover, Georgia Section 305.1.1 requires a complete permanent barrier complying with Section 305.2 before filling and operation.

• Openings and climb resistance: Barrier openings cannot pass a four-inch sphere. Solid barriers cannot have handholds/footholds apart from normal construction tolerances and tooled masonry joints.

• Screen enclosures: A compliant enclosure may form all or part of the barrier and must be designed by a registered design professional. Enclosure walls are not dwelling walls. Barrier mesh must have tensile strength of at least 100 lb/ft² under ASTM D5034 and ball-burst strength of at least 150 lb/ft² under ASTM D3787.

• Mesh barriers: Non-chain-link mesh fences must follow manufacturer instructions and ASTM F2286; hinged gates must satisfy Section 305.3. Mesh fencing cannot be installed atop onground residential pools. Its inside face must be at least 20 inches from the nearest water edge.

• Horizontal and vertical members: Where the distance between tops of horizontal members is less than 45 inches, horizontal members belong on the pool side and vertical openings/decorative cutouts cannot exceed 1¾ inches. At 45 inches or more, vertical openings cannot exceed four inches and decorative cutouts cannot exceed 1¾ inches.

• Chain-link and diagonal barriers: Pool-barrier chain-link openings cannot exceed 1¾ inches; slats fastened at top/bottom must reduce openings to that limit. Diagonal-member openings also cannot exceed 1¾ inches, and diagonal members cannot exceed 45 degrees from vertical.

• Equipment clear zone: Equipment on the same lot outside the barrier, including pool pumps, filters and heaters, must be at least 36 inches from the barrier’s outside.

• Doors and gates: Barrier doors/gates must accommodate a locking device. Pedestrian access must open away from the pool, self-close and self-latch; doors/gates cannot swing over stairs. Service/utility gates stay locked when unused. Double/multiple gates require at least one secured leaf and a self-latching adjacent leaf.

• Latch release: Under Georgia’s replacement Section 305.3.3, an outside-accessed, non-self-locking release at a residential pool/spa must be at least 54 inches above finished floor or ground. For an inside release, openings in the gate, door and barrier within 18 inches of the latch cannot exceed ½ inch in any dimension.

• Dwelling or structure walls: Where a wall forms part of the barrier and openings give direct pool access, Section 305.4 provides safeguards using the specified UL 2017 water-hazard entrance alarms, an ASTM F1346 listed/labeled safety cover, or approved protection affording the required equivalent protection. Operable windows with sills below 48 inches, doors and gates are within the alarm provision. Alarm-deactivation controls in ordinary dwellings are at least 54 inches above the floor; in required Accessible/Type A/Type B dwellings, they are 48–54 inches.

• Onground pool walls and access: A pool wall serving as the barrier must sit on grade, reach at least 48 inches around the entire perimeter, comply with Section 305.2 and be allowed for that purpose by the manufacturer. A barrier atop the pool wall must likewise reach at least 48 inches and comply with the applicable requirements and manufacturer instructions. Ladders/steps must be securable, lockable or removable unless enclosed by a compliant barrier; openings left by their securing/removal cannot pass a four-inch sphere.

• Natural barriers: The natural-waterbody exception requires no public shoreline access and barriers extending at least 18 inches beyond the water’s edge. A natural topographic barrier requires governing-body approval and protection at least equivalent to Sections 305.2–305.5.

• Existing pools and alterations: Georgia Section 300 preserves qualifying lawful existing installations that remain safe and are used/maintained consistently with their original design. Required safeguards must be maintained under the edition applicable to their installation. Covered additions/alterations/repairs follow the stated new-work requirements and cannot make the existing system unsafe. The historic-pool provision requires the code official’s safety and public-interest determination.

PRIVATE RESTRICTIONS

HOA covenants, deed restrictions, private subdivision restrictions, architectural-review covenants, recorded private easements, conservation easements, agricultural agreements and private boundary agreements operate independently and may be more restrictive than city requirements. City approval does not determine private boundary rights or remove obligations under those instruments.

Public subdivision buffers, approved development conditions and public utility/drainage easements are separate from private covenants. Both public requirements and applicable private restrictions can affect a proposed fence.

REVIEW AND ENFORCEMENT CONTEXT

Fence issues are typically reviewed during permit or approval review when required, and through complaint-based code enforcement. Examples include:

• Permit and plan review: The codes enforcement officer reviews fence location, height, materials, access and other applicable conditions under the city permit process.

• Street visibility and access: Reviews may address intersection clear vision, adjoining owners’ driveway views, public rights-of-way, utility meters, garbage/mail access and required parking.

• Special property conditions: Reviews may involve PUD plans, subdivision buffers, required screening, floodplain/floodway encroachments, wetlands, water-supply buffers and covered nonexempt disturbance.

• Pool and facility barriers: Reviews may address permanent pool-barrier timing, gate/latch operation, openings, climb resistance, covers or the separate detention-pond specifications.

• Unsafe fences: Structurally unsound fences or fencing hazardous to children can be addressed through nuisance enforcement. Under Section 100-7, the codes enforcement officer gives written notice identifying the violation and corrective action; further authorized compliance measures may follow. Section 16-2 also authorizes the stated city officers and inspectors to investigate nuisance complaints and issue citations.

USING THIS INFORMATION

This page provides general orientation on how residential fence rules are structured and applied within the City of Bremen, Georgia. Updated October 2026.

In addition to local fence rules, certain Georgia laws apply statewide. See Statewide Fence Laws in Georgia.

It is not legal advice and does not replace official ordinances, permits, approvals, surveys, or professional guidance. Rules and interpretations may change, and application may vary based on zoning district, site conditions, subdivision/land-development status, easements, rights-of-way, drainage or stormwater conditions, floodplain/floodway status, erosion/sediment or land-disturbance requirements, stream or state-water buffers, historic/design/special-district status, consolidated-government scope where applicable, pool-barrier use, utility-excavation requirements, road/highway conditions, and private restrictions such as HOA covenants or deed restrictions. Before purchasing materials or beginning construction, confirm current requirements and site-specific limitations with the City of Bremen codes enforcement officer and any applicable private agreements. If this page conflicts with official ordinances, published guidance, adopted district guidelines, or direction from the City of Bremen codes enforcement officer, the official sources control. For legal advice or legal interpretation, consult a licensed attorney.